October 6, 2014
Summary of Mission Events
![]() | January 2014 | Who's Next? |
![]() | July 3, 2012 | SMOS satellite measurements improve as ground radars switch off |
![]() | November 17, 2010 | One year ago, SMOS was switched on and delivered its first "image" |
![]() | September 30, 2010 | Inauguration of SMOS satellite CATDS in Brest |
![]() | End of January 2010 | Successful end of in-flight commissioning review for SMOS system |
![]() | November 2, 2009 | Launch |
![]() | November 2009 | Launch acceptance review |
![]() | October 2009 | CATDS Production and distribution center delivery to IFREMER |
![]() | Mid-September to November 2009 | Launch campaign at Plesetsk launch site |
![]() | September 16, 2009 | Shipment of the Satellite to Plesetsk launch site |
![]() | August 2009 | Consolidation of SMOS launch date |
![]() | May 2009 | Mission Flight Acceptance Review |
![]() | April 2009 | Operation Readiness Review |
![]() | October 2008 to November 2009 | In orbit Operations preparation |
![]() | February 2009 | Launcher Final Mission Analysis Delta Review |
![]() | July 2008 to September 2009 | Storage of the Satellite in Thalès Alenia Space premise in Cannes |
![]() | July 2008 | Satellite Qualification Review |
![]() | May 2008 | ITT for the CATDS L3 and 4 Operational processors |
![]() | July 2007 - June 2008 | Satellite Flight Model integration and tests (Vibration, Thermal Vacuum, EMC) at Thalès Alenia Space Cannes facilities |
![]() | April 2008 | The launch date of SMOS has been officially confirmed by ESA in April 2009 |
![]() | 5-7 March 2008 | Satellite System Validation Test (SSVT) 1 |
![]() | February 2008 | Delivery Key Point Data Processing Ground Segment V1 |
![]() | November 2007 | Signature with IFREMER of an agreement for SMOS. |
![]() | July 2007 - April 2008 | Satellite Flight Model integration and tests (Vibration, Thermal Vacuum, EMC) at TAS Cannes facilities Pictures of the tests and integration |
![]() | June 2007 | Susanne Mecklenburg has been nominated as SMOS Mission Manager at ESA ESRIN |
![]() | June 2007 | Payload Flight Model delivery at Cannes |
![]() | May 2007 | Launcher Final Mission Analysis Review |
![]() | April 2007 | SMOS Platform Flight Model delivery |
![]() | March 2007 | System Tests Qualification Key Point |
![]() | January 2007 - June 2007 | Payload Flight Model environment Test (Vibration, Thermal Vacuum, EMC) at ESTECfacilities |
![]() | December 2006 | SMOS Satellite Operations Ground Segment (SOGS) delivery to the operation team |
![]() | November 2006 | Level 2 Ground Segment Quality Review |
![]() | Summer 2006 | SMOS Satellite Critical Design Review |
![]() | March 2006 | Launcher Preliminary Mission Analysis Review |
![]() | February 2006 | Start of the Activities of Integration and Tests of SMOS Platform Flight Model |
![]() | February 2006 | Overal Ground Segment Preliminary Design Review |
![]() | February 2006 | SMOS LEVEL 2 processors Critical Design Review |
![]() | January 2006 | DPGS Preliminary Design Review |
![]() | November 2005 | Satellite Operations Ground Segment definition Key point |
![]() | October 2005 | Payload Critical Design Review |
![]() | September 2005 | Start of Satellite Phase C |
![]() | September 2005 | SMOS LEVEL 2 soil moisture processor Preliminary Design Review (Toronto Canada) |
![]() | June 2005 | Payload environment Test on development models (Vibration, Thermal Vacuum, EMC) |
![]() | March-September 2005 | Satellite Phase B/C Bridging phase |
![]() | March 2005 | Satellite Preliminary Design Review |
![]() | December 2004 | ESA's IPC go ahead to procure a launch vehicle from Eurockot |
![]() | October 2004 | Start of Satellite Phase B |
![]() | September 2004 | SMOS seminar held in Lisboa, Portugal |
![]() | August 2004 | Notification of CNES/ALCATEL contract for Satellite Phase B/C/D activities |
![]() | June 2004 | Start of payload construction Phases C/D |
![]() | April 2004 | ESA / CNES Mission Preliminary Design Review |
![]() | November 2003 | Approval for full implemention |
![]() | October 2003 | End of payload Phase B, design completed |
![]() | November 2001 | End of payload Phase A with scientific and technical review. Recommendation received to proceed with implementation. |
![]() | November 2001 | EuroSTARSS 01 campaign. |
![]() | October 2000 | Start of payload feasibility studies (Phase A) |
![]() | April 1999 | Selection of SMOS |
![]() | July 1998 | Call for proposals |
Published in: